Answer:
1. $8.25
2. $313,500
Explanation:
Given that,
Variable overhead cost per direct labor-hour = $2.00
Total fixed overhead cost per year = $250,000
Budgeted standard direct labor-hours (denominator level of activity) = 40,000
Actual direct labor-hours = 39,000
Standard direct labor-hours allowed for the actual output = 38,000
1. Total overhead cost at denominator level of activity:
= Total fixed overhead + Total variable overhead
= $250,000 + (40,000 × $2.00 )
= $250,000 + $80,000
= $330,000
Predetermined overhead rate:
= Total overhead cost at denominator level of activity ÷ Budgeted standard direct labor-hours
= $330,000 ÷ 40,000
= $8.25
2. Overhead applied:
= Standard direct labor-hours allowed for the actual output × Predetermined overhead rate
= 38,000 × $8.25
= $313,500