Three processes have the following costs: Process A has a fixed cost of $2,000 and variable cost of $3.00/unit. Process B’s fixed cost is $4,000 and variable cost is $2.60/unit. Process C’s fixed cost is $8,000 and variable cost is $2.40/unit. If the projected total demand is for 6,000 units, which process should be used?