Answer:
multi factory productivity= 2.37
Explanation:
Giving the following information:
10,000 Units Produced
Sold for $10/unit
500 labor hours
Labor rate: $9/hr
Cost of raw material: $30,000
Overhead: $15,50
To calculate the multi factory productivity, we need to use the following formula:
multi factory productivity= output/ (labor + material + overhead)
multi factory productivity= (10,000*10) / (4,500 + 30,000 + 7,750)
multi factory productivity= 2.37