Answer:
$18,300
Explanation:
Data provided in the question
Direct labor cost = $15,000
Overhead application rate = 122%
By considering the above information, the allocated overhead is
= Direct labor cost × Overhead application rate
= $15,000 × 122%
= $18,300
By multiplying the direct labor cost with the overhead application rate, the allocated overhead could come