Respuesta :
Answer:
Job HE-65 total cost 900 dollars
Explanation:
predeterminated overhead rate:
expected cost / expected driver
900,000 / 30,000 = $30
Each labor hour generates $30 dollars of overhead according to our expectation
Now we solve for the cost of job HE-65
materials 300
labor 15 hours x $10 = 150
and overhead 15 hours x $30 each = 450
total cost 300 + 150 + 450 0 900
Answer:
$900
Explanation:
costs for Job HE-65:
direct materials = $300
direct labor = 15 x $10 = $150
applied overhead = ??? = $30 per labor hour x 15 labor hours = $450
⇵
if we apply predetermined overhead rate based on direct labor hours, then we should apply $900,000 / 30,000 = $30 per labor hour.
the total costs for JOB HE-65 = $300 + $150 + $450 = $900