Answer:
20 days
Step-by-step explanation:
Expected Task duration
= (O + 4 M + P)/6
Where O = best case scenario = 15 days
P = worst case scenario = 25 days
M = Usual scenario = 20 days
Therefore, expected task duration
= [15 + 4 (20) + 25] ÷ 6
= 120 ÷ 6
= 20 days.
Therefore expected task duration is 20 days.