Dale, a design engineer at a machinery manufacturing company, prepares a plan with a detailed estimate of the overheads and resources required for setting up a stall at a machinery exhibition next month. In this scenario, Dale has most likely prepared a _____.

Respuesta :

Answer: Single-use plan

Explanation:

  According to the given scenario, the Dale is one of the design engineer in the manufacturing firm and the main role of the dale is preparing the particular plan by explaining the detailed estimation of the resources.

The single use plan is one of the type of method that is used in an organization that helps in achieving the specific objective of the firm and it is used in the one situation.

The advantage of using the single-use plan it makes the program less complex and also able to solve the various types of large type of projects.

 Therefore, Single-use plan is the correct answer.