Answer:
1.- 68 per setup
26.08 per machien hour
15.95 per labor hour
2)
Rims unit cost: $ 32.92
Posts: $ 25.40
Explanation:
First we calcualte the activity rates:
[tex]\left[\begin{array}{ccccc}$Activity&$Driver&$cost&$Total&$Rate\\$Machine Setups&setups&27200&400&68\\$Special processing&machine-hours&130400&5000&26.08\\$General factory&labor-hours&1053000&66000&15.95\\\end{array}\right][/tex]
Then, we solve for the total overhead allocated:
[tex]\left[\begin{array}{cccccc}Activity&Posts&Rims&Allocate Rims&Allocate Posts\\Machine Setups&280&120&8160&19040\\Special processing&0&5000&130400&0\\General factory&61000&5000&79772.73&973227.27\\Total&&&218332.73&992267.27\\\end{array}\right][/tex]
We now divide by the amount produced to get the manufacting overhead per unit.
218,332.73 / 22,000 = 9.924215 = 9.92
992,267.27 / 80,000 = 12,403340 = 12.40
Now, we calcualte labor per unit:
0.6 x $15 = 9
0.2 x $15 = 3
Rims unit cost:
14 materials + 9 labor + 9.92 overhead = 32.92
Posts:
10 materials + 3 labor + 12.40 overhead = 25.40