Answer:
14.4 covers/hr.
Explanation:
First, we need to identify how much covers are produced in 1 hour, which will be total produced divided by the total time:
covers/hr = 120/10
covers/hr = 12
If the production will be increased by 20%, it means that new production will be the initial one plus 20% (0.20) of it:
12 + 0.20*12 = 14.4 covers/hr.