The addition of acceptance criteria factors to the milestone schedule in a project charter helps the team understand who will judge the quality of the deliverable associated with each milestone, and _______.

Respuesta :

It is associated with each milestone and the criteria or the standards they will use

Explanation:

Acceptance criteria are usually added by the product owner or the stake holder and then it is not necessary that all items or the products must contain the acceptance criteria and it do not make that much difference

The criteria are the different situations in which there will be a judgement based on the factor that will remain as the factor to determine the quality and then the standard in which they will be used