A production line is to be designed for a job with three tasks. The task times are .3 minutes, 1.4 minutes, and .7 minutes. For a single production line with no parallel activities, the minimum cycle time in minutes is:
A. 0.3
B. 0.7
C. 1.4
D. 2.4
E. 0.8