A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the
Sprint planning meeting?

a. Sprint Backlog, collection of tasks
b. Product Backlog, collection of tasks
c. Sprint Goal, Sprint Backlog
d. Product Backlog, Sprint Backlog

Respuesta :

Answer:

The correct answer is letter "C": Sprint Goal, Sprint Backlog.

Explanation:

Sprint Planning is the first event where the task to be done in the course of the sprint is planned. In this meeting, the Scrum Master, Product Owner, and the Developing team meet. After brainstorming, the Sprint goal is set during the first half of the planning. In the second half, the Sprint backlog is created to establish the steps that will be taken in the effort of achieving the Sprint plan.