High-Low Cost Estimation The Stone Company has observed that its utility cost is $5,000 when operating at a level of 20,000 machine hours per period. The utility cost drops to $4,000 when the operating level drops to 15,000 machine hours. Required: Estimate the utility cost for an operating level of 18,000 machine hours.

Respuesta :

Answer:

$4,600

Explanation:

High-Low cost estimation is used to split a mixed cost into variable cost and fixed cost.

The first step is to determine the variable cost per unit with this formula

=  High Activity cost - Low Activity Level cost

  _____________________________________

   High Activity Level (units) - Low Activity Level (units)

In this case, we can slot in the appropriate figure using this formula

=  $5,000    -        $4,000

   __________________

   20,000hrs - 15,000hrs

= $,1000

  ______

  5000hrs

= $0.2hr

Using high-low cost estimation, the variable cost per machine hour is $0.2.

Now since total cost equals fixed plus variable cost, we can get our fixed cost by multiplying variable cost per machine hour with activity level and deducting the result from total cost given.

Using the high activity level (20,000), our fixed cost will be:

Fixed cost  = Total cost - variable cost per machine hr (activity level)

Fixed cost= $5,000 - $0.2(20,000hr)

Fixed cost = $5,000- $4,000

Fixed cost =$1,000

Having gotten our fixed cost and variable cost per machine hour, we can estimate the total utility cost for 18,000 machine hours by using this formula:

y = a + b(x)

Where y is the total cost, a the fixed cost, b the variable cost per unit and x the activity level.

y = $1,000 + $0.2(18,000)

y = $1,000 + 3,600

y = $4,600.

ACCESS MORE