Respuesta :
Answer:
12 assemblers will take six hours to complete that same job.
Step-by-step explanation:
For answering this question correctly, we will use Inverse Rule of Three because the less assemblers work, the more time it takes to complete the job.
Assemblers Hours
18 4
12 x
*******************************
12x = 18 * 4 (It's Inverse, remember)
12x = 72
x = 72/12
x = 6 hours
12 assemblers will take six hours to complete that same job.
The number of hours that will be used by 12 assemblers to complete the job will be 6 hours.
Based on the information given, let the number of hours used by 12 assemblers be represented by x.
Therefore, the equation to solve the question will be:
18/12 = x/4
Cross multiply
12x = 18 × 4
12x = 72
x = 72/12
x = 6
Therefore, 6 hours will be used.