Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost.A. TrueB. False

Respuesta :

gerald4764
gerald4764 gerald4764
  • 24-01-2020

Answer: False

Explanation: Because fast-tracking doesn’t involve additional resources, it’s usually best to start with this technique while Crashing requires careful planning to prevent “panic mode” among the project crews and to avoid acceleration claims.

Answer Link

Otras preguntas

How do u simplify the square root of 1008
Is a penny soluble in water
Barbara has 9 stuffed animals. Trisha has 3 times as many stuffed animals as Barbara. How many stuffed animals does Trisha have? Please help.
In which type of government structure do local states have the greatest power?
whats x-y=-3 and whats 2x+y =12
Complete the sentence 7 is 1/10 of
C=48y+.99n Wat is the y someone pls solve for y
how can you write 310,763,163 in word form
How do u simplify the square root of 1008
The team (selects,select) their officers by secret ballot. Which verb agrees with the collective noun?