Answer:
The materials and supplies in the planning budget for November
= $2,090 + $15 per vehicle
= $2,090 + $15 x 89 vehicles
= $2,090 + $1,335
= $3,425
The correct answer is D
Explanation:
The materials and supplies in the planning budget are comprised of a fixed cost of $2,090 plus a variable cost of $15 per vehicle. The number of vehicle budgeted for was 89 vehicles. Thus, the materials and supplies in the planning budget will be $2,090 plus $1,335 x 89 vehicles.