Respuesta :

Answer:

Lumpy demand is not used in project management.

The correct answer is  D

Explanation:

Dummy is a zero activity, which helps in network analysis.

Activity refers to a task in network analysis.                                                              

Latest finish time is the latest completion time of a project in network analysis.

Lumpy demand refers to low demand as a result of higher cost. It is not used in network analysis (project management)