Answer:
d. 28
Explanation:
The computation of the reorder point is shown below:
= Demand × lead time + safety stock
where, Demand equal to
= Expected demand ÷ total number of weeks in a year
= 420 tires ÷ 52 weeks
= 8.07692
So, the reorder point would be
= 8.07692 × 1 + $20
= 28 units
We simply multiplied the demand with the lead time and then added to the safety stock