Answer:
Crash the schedule.
Explanation:
Fast-track can complete the task earlier but takes more money. Assign more experienced people will cost the management more money. Cut scope reduces the project requirement and finishes the task earlier. Therefore, options A B and D can not be the answer.
Crash the schedule (option C) is the answer because it allocates enough resources to complete the task earlier without spending more money.