Answer:
B-False
Explanation:
After the retrospective discussion all the improvement items discussed are placed in the Product Backlog. To ensure continuous improvement, the next sprint backlog ( & not the current one) should include at least one high priority process improvement which was identified in the previous Sprint Retrospective meeting.