Answer:
14.5 hours.
Explanation:
Given that,
Move time = 3.4
Wait time = 11.2
Queue time = 7.6
Process time = 2.3
Inspection time = 1.2
Throughput time:
= Process time + Move time + Inspection time + Queue time
= (2.3 + 3.4 + 1.2 + 7.6)
= 14.5 hours.
Therefore, the throughput time for the Schapp corporation was 14.5 hours.