FLEXIBLE BUDGET REPORT
Flexible budget Actual Variance
Activity level (units) 10,800 10,800 No variance
$ $
Sales 864,000 885,000 21,000(F)
Less: Variable cost:
Total variable cost 378,000 351,000 27,000(F)
Less: Fixed cost:
Total fixed cost 270,000 285,000 15,000(U)
Profit 216,000 249,000 33,000(U)
Explanation:
In this report, the budgeted total variable cost is obtained by multiplying the variable cost per unit by the quantity of goods produced and sold.
The total fixed cost remains constant regardless of the quantity produced and sold.
Variance is the difference between the flexible budget and actual results.