Answer:
Explanation:
However, Job 2 can be completed at time 3 which is late by 1 hour.
Suppose that the processing times are exponentially distributed.
Let
Expected make span is minimized by processing the jobs in the descending (high to low) order of processing
Make span is the completion time of the last job processed. Although make span is defined as a completion time of a job, it actually measures how long the production facility should remain open.