Answer:
The number of hours that the firm use to work on the product during the second month is
B. 303.9 hours
Step-by-step explanation:
Given;
Time taken to complete the first unit of product = T1
T1 = 80 hours
Time taken to complete the first n unit of product = Tn
Learning factor = 75%
Learning curve coefficient for total time = C
Therefore, Tn is given as
Tn = T1(C)
Time taken to work on the product for the second month T*= (T22 - T10)
T22 = T1(C22)
T10 = T1(C10)
T* = T22-T10 = T1(C22 - C10)
T* = 80( 9.388 - 5.589)
T* = 303.9096
T* = 303.9 hours