In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units.
Which of the following is the capacity requirement for a week at Work Center B?
a. 101b. 151c. 201d. 251

Respuesta :

Answer:

201 hours.

Explanation:

Given: Order size of work for a week is 2000 units.

          Setup time is 1 hour.

Now, lets calculate the capacity requirement for a week at work centre B.

Formula; Capacity= [tex][set\ up\ time+(labour\ per\ unit \times total\ unit\ of\ work)][/tex]

Substitute the value in the formula.

⇒Capacity= [tex][1+ (0.10 \times 2000)][/tex]

⇒ Capacity= [tex][1+(200)] = 201\ hours[/tex]