Answer:
201 hours.
Explanation:
Given: Order size of work for a week is 2000 units.
Setup time is 1 hour.
Now, lets calculate the capacity requirement for a week at work centre B.
Formula; Capacity= [tex][set\ up\ time+(labour\ per\ unit \times total\ unit\ of\ work)][/tex]
Substitute the value in the formula.
⇒Capacity= [tex][1+ (0.10 \times 2000)][/tex]
⇒ Capacity= [tex][1+(200)] = 201\ hours[/tex]
∴ 201 hours is the capacity requirement for a week at work centre B.