Answer:
A) Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
Explanation:
If the project manager uses finish to finish relationships, a successor activity cannot finish until the predecessor activity has not finished.
If the project manager uses start to start relationships, a successor activity cannot start until the predecessor activity has not started.
If the project manager uses start to finish relationships, a successor activity cannot finish until the predecessor activity has not started.
Answer:
Overlap sequential activities using finish-to-finish relationships
Explanation:
Overlap sequential activities using finish-to-finish relationships. This overlaping does not account for unexpected events and might not account possible relations between the legs or stages of a project