XYZ company uses "Continuous Review System (Q, ROP)" for an item. Lead-time is currently one week. The average demand during the week is 100 units with a standard deviation of 20 units. If the supplier increases lead-time to 4 weeks, what will be the standard deviation of lead-time demand?
a.40 80
b.17.89
c.44.72
d.120