Answer:
The manufacturing cycle efficiency is 23.53%.
Explanation:
Step 1 of 2
Throughput time includes process time of 4 days plus inspection time of 2 days plus move time of 3 days plus queue time of 8 days which gives throughput time of 17 days. The company’s product takes 17 days to pass through the manufacturing process.
Step 2 of 2
Calculation of manufacturing cycle efficiency.
Manufacturing cycle efficiency = Process time / Throughput time
= 4 days / 17 days
=23.53%
Thus, manufacturing cycle efficiency is 23.53%.