Answer:
D) 9.7 hours
Explanation:
It is a time period which is taken to manufactured the product
The computation of the throughput time is shown below:
= Move time + Queue time + Process time + Inspection time
= 3.2 + 5.1 + 1.2 + 0.2
= 9.7 hours
It is a combination of the move time, queue time, process time, and the inspection time.
All other information which is given is not relevant. Hence, ignored it