Answer:
7 days
Explanation:
Although the lead time for assembling a finished cartridge is only 2 days, the assembly process cannot begin until all child items are available. Thus, the time that would take Bartran to create at least one finished ink cartridge if it started with nothing in stock is the highest lead time of all child items added to the lead time of assembly.
Labels have the highest lead time of 5 days, therefore the total time taken is:
5 +2 = 7 days