Answer:
3,220 units
Explanation:
The computation of the material quantity variance is shown below:
Direct material quantity variance = Standard Price × (Standard Quantity - Actual Quantity)
$750 = 2 gallons × $12.50 × (6,500 gallons ÷ 2 - actual quantity)
$750 = $25 × (6,500 gallons ÷ 2 - actual quantity)
$30 = 3,250 - actual quantity
So, the actual quantity would be
= 3,250 - $30
= 3,220 units
The Standard Price is computed below:
= 2 gallons × $12.50
The standard quantity is computed below:
= 6,500 gallons ÷ 2
= 3,250 units