Which of the following process groups
A) Consists of those processes performed to establish the total scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives.
B) The PM plan and project documents developed as outputs for the Planning Process Group will explore all aspects of the scope, time, cost, quality, communications, human resources, risks, procurements and stakeholder engagement.

Respuesta :

Answer:  The correct answer is :  Planning Process Group

Explanation:  The main result of the planning process is the integrated project plan that includes the scope, schedule, quality, human resources, budget, communication, procurement plans and risk management. The planning processes develop the project management plan and the project documents necessary to carry it out.