Answer:
7 workers will be required
Explanation:
We will define actual time required to do a job
= Standard time required for producing each unit x Worker efficiency (%)/100
= 11.65 x 115/100
= 13.3975 minutes
Total available minutes in 4 days = 4 days x 8 hours/ day x 60 minutes / day = 1920 minutes
Therefore ,
Number of units which can be produced by 1 worker in 4 days = 1920 /13.3975
Number of units to be produced = 1000 units
Therefore,
Number of workers required
= Number of units to be produced / Number of units which can be produced by 1 worker in 4 days
= 1000 x ( 13.3975 /1920)
= 6.977 ( 7 rounded to nearest whole number )