An ​x-bar control chart was examined and no data points fell outside of the limits. Can this process be considered in​ control?
a.Not​ yet, there could be a pattern to the points.
b.Not​ yet, the ​R-chart must be checked.
c.Not​ yet, the number of samples must be known.
d.Yes. Both A and B

Respuesta :

waidigbenro waidigbenro
  • 16-11-2019

Answer:

d.Yes. Both A and B

Answer Link

Otras preguntas

What were the economic political and social causes of the cold war?
What do you think the answer is?
The formula for lithium oxide is A) Li2O B) LiO2 C) LiO D) Li2O3
If a 375 mL sample of water was cooled from 37.5 degrees Celsius to 0 degrees Celsius , how much heat was lost (in joules)
Solve the following radical: 5√13 - 9√13
Which of the following modern movements led to new ways of studying and thinking about the natural world?
128oz equals how many pints
I need help finding the area in all 6 shapes, do not include the blue square, that is a pond, the person who answers them all gets BRAINLIEST answer!!
Name the war that is considered to be most destructive conflict of the reformation era?
Write a real world problem that compares 0.4 and 0.29. Then solve the problem.