Answer:(a) The correct answer is (D) All of the above
b) : The correct answer is option (B). (c) : The correct answer is option (A). (d) : The correct answer is option (B) (e) : The correct answer is option (C)
Explanation:
Cost Estimating Relationship or βCERβ means a mathematical expression of varying degrees of complexity expressing cost as a function of one or more variables.
The relationship may utilize cost-to-cost variables, such as quality assurance hours to manufacturing hours, cost-to-non-cost variables, such as engineering hours to the number of engineering drawings, or non-cost to non-cost, such as pounds of thrust to weight.
Variables can be referred to as, numerator and denominator, dependent and independent, or pool and base.