Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by?

Respuesta :

Answer:

Imposed project deadlines.

Explanation:

The term of project management imposed deadline refers mainly to the calendar-based dividing line used to determine a fixed time or date on which the project management team has projected and/or developed that the particular schedule of work and/or schedule of work events.