51. A positive quantity in the current period’s planned order row means that ___________________. a) lead time is too long b) the projected available is negative c) gross requirements are too large d) the planned order is due to be completed in the current period e) an order must be released

Respuesta :

Answer:

The correct option is E

Explanation:

A positive quantity means that the order is confirmed and in the present period for the planned order row states or described that the order must to be delivered or need to be released. The current period is the action bucket as it is that period where it requires to take action like rescheduling, cancelling or releasing the orders.