Answer:
The correct option is A.
Explanation:
The cost baseline is the total of cost of work packages and works as reference point, it does not consider the future variances in the activities of the project. Therefore, it does not allocate the cost estimates to the activities of the future operations. It is only used to monitor the planned and the actual cost of the project.