Which of the following is the estimate of the minimum amount of time it would take to perform a task? (Points : 2) Minimal duration
Optimistic duration
Pessimistic duration
Expected duration
Earliest completion

Respuesta :

Answer:

Optimistic duration

Explanation:

The following three concepts are Project management concepts:

Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.

Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc

Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.

Which of the following is the estimate of the minimum amount of time it would take to perform a task?

The answer is Optimistic duration