Answer:
Estimated manufacturing overhead rate= $1.53 per machine hour
Explanation:
Giving the following information:
The company allocates manufacturing overhead using a single plantwide rate with machine hours as the allocation base.
The estimated overhead costs for the year are $ 104,000.
Machine hours (MHr)= 27,000 + 41,000= 68,000 machine hours
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 104,000/68,000= $1.53 per machine hour