Answer:First Vendor
Step-by-step explanation:
Given
company acceptable range
Upper control limit=90 minutes
Lower control limit=50 minutes
Mean of first vendor=74 minutes
standard deviation[tex](\sigma _1)=4 minutes[/tex]
Mean of second vendor=72 minutes
Standard deviation[tex](\sigma _2)=5.1 minutes[/tex]
To find better vendor we use Process capability index which is given by
[tex]C_{pk}=min. \left ( \frac{UCL-mean}{3\times Standard\ deviation},\frac{mean-LCL}{3\times Standard\ deviation}\right )[/tex]
[tex]C_{pk}=min\left ( \frac{90-74}{3\times 4},\frac{74-50}{3\times 4}\right )[/tex]
[tex]C_{pk}=min\left ( 1.33,2\right )[/tex]
The Process capability index for first vendor is 1.33
For Second Vendor
[tex]C_{pk}=min. \left ( \frac{UCL-mean}{3\times Standard\ deviation},\frac{mean-LCL}{3\times Standard\ deviation}\right )[/tex]
[tex]C_{pk}=min\left ( \frac{90-72}{3\times 5.1},\frac{72-50}{3\times 5.1}\right )[/tex]
[tex]C_{pk}=min\left ( 1.176,1.43\right )[/tex]
The process capability index of Vendor 2 is 1.176
Thus Vendor is chosen over vendor 2 because its Process capability index is higher