Answer:
Allocated overhead= $1,430,600
Explanation:
Giving the following information:
The company's executives estimated that direct labor would be $3,750,000 (250,000 hours at $15/hour) and that factory overhead would be $1,550,000 for the current period.
The records show that there had been 230,000 hours of direct labor.
Using direct labor hours as a base.
Predetermined overhead rate= total estimated manfacturing overhead for the period/ total amount of allocation base
Predetermined overhead rate= 1555000/250000= $6.22 per hour
Allocated overhead= Predetermined overhead rate*actual hours= 6.22* 230000= $1,430,600