Which of these is NOT one of the four purposes of a project charter? a. Help the project manager, sponsor, and any team members that are already assigned develop a common understanding. b. Authorize the project manager to proceed c. Quickly screen out obviously poor projects d. Provide a detailed blueprint to guide project execution

Respuesta :

Answer:

The answer is: C) Quickly screen out obviously poor projects

Explanation:

The statement "Quickly screen out obviously poor projects" has to do with a project´s evaluation stage, where it is determined if the project is positive and should be carried out or on the contrary it should be rejected.

A project charter serves as a reference document of an already approved project that is being carried out or will be carried out in the future.