Answer:
Total estimated costs = Suncoast incurred costs + estimated future costs
= $380,000 + $570,000
= $950,000
Contract price = $900,000
Loss = Total estimated costs - Contract price
= $950,000 - $900,000
= $50,000
The project is unprofitable.
[tex]Percentage\ of\ completion\ method=\frac{Costs\ incurred}{Total\ estimated\ costs}[/tex]
[tex]Percentage\ of\ completion\ method=\frac{380,000}{950,000}[/tex]
= 0.4
= 40%
Construction revenue in 2017 = contract price × percent complete
= $900,000 × 40%
= $360,000
The entire loss is recognized under two methods for an unprofitable project.
The journal entries are as follows:
(a) Construction expense A/c Dr. $410,000
To Construction in process $50,000
To Construction Revenue $360,000
(To record entire loss on overall unprofitable contract)
(b) Loss from contract A/c Dr. $50,000
To Construction in process $50,000
(To record entire loss on overall unprofitable contract)