Answer:
The applied overhead is $231,000
Explanation:
The computation of the applied overhead is shown below:
= Predetermined overhead rate × direct labor hour
= $42 × 5,500 hours
= $231,000
Since the predetermined overhead rate is given in the question, so there is no need to re calculate it.
And, the other items which are mentioned in the question are not considered in the computation part. Hence, these items would be ignored