contestada

Tenderfoot company uses a job costing system. The work in process inventory on December 31, 2012 consisted of Job No. 175. This job had been charged with direct materials of $17,400 and direct labor of $20,000. Overhead is charged at a rate of 80% of direct labor cost. The cost of Job No. 175 was:

Respuesta :

Answer:

Total cost= $53,400

Explanation:

Giving the following information:

Job No. 175:

This job had been charged with:

Direct materials of $17,400

Direct labor of $20,000.

Overhead is charged at a rate of 80% of direct labor cost

Total cost= direct labor + direct materials + manufacturing overhead

Total cost= 20000 + 17400 + (0.80*20000)= $53,400

ACCESS MORE
EDU ACCESS
Universidad de Mexico