Which of the following does not describe a constraint? Question 1 options: 1) Project team actions are dictated. 2) It may regard budget, resources, or schedule. 3) Project team actions are restricted. 4) Project situations are believed to be true

Respuesta :

Answer:

1) Project team actions are dictated

Explanation:

According to the exercise the project actions are not dictated, they are decision in with all the team work.

The budget, resources or schedule (time) are constraints  

Project team actions are restricted the actions are limited  

Project situations are believed to be true, could happened different types of situations  

As you can see the constraints limited the project in its operation but do not without a manageable things.

ACCESS MORE