Respuesta :
Answer:
The materials price variance for the month is $1,295 favorable and the materials quantity variance for the month is $3,744 unfavorable
Explanation:
1. The formula to compute the material price variance is shown below:
= (Standard Price - Actual Price) × Actual Quantity
where,
Standard price is $12.00 per pound
Actual price is not given, so we have to compute it by using the formula which is shown below:
= Actual cost of materials used in production ÷ Actual materials purchased
= $43,105 ÷ $3,700 pounds
= $11.65
And, the actual quantity is 3,700
Now apply these values to the above formula
So, the answer would be
= ($12 - $11.65) × 3,700
= 0.35 × 3,700
= $1,295 favorable
2. The formula to compute the material quantity variance is shown below:
= (Standard Quantity - Actual Quantity) × Standard Price
where,
Standard quantity is not given, so we have to compute it by using the formula which is shown below:
= Actual output × Standard quantity per unit of output
= 560 units × 4.8 pounds
= 2,688
The Actual quantity is 3,000
And, the standard price is $12.00 per pound
Now apply these values to the above formula
So, the answer would be
= (2,688 - $3,000) × $12
= 312 × $12
= $3,744 unfavorable
Hence, the materials price variance for the month is $1,295 favorable and the materials quantity variance for the month is $3,744 unfavorable