Answer:
The Cpk for the process is 1.61
Step-by-step explanation:
The formula for Cpk is:
[tex]Cpk=min(\frac{USL-mean}{2*stdDev},\frac{mean-LSL}{2*stdDev} )[/tex]
In this case in specific that we can test the capability of the process for 2 standard dev we modify the formula to adjust it:
so for this formula:
average: 23.546
USL: 23.23+0.612=23.842
LSL: 23.23-0.612=22.618
standard dev=0.092
So,
[tex]Cpk=min(\frac{23.842-23.546}{2*0.092} , \frac{23.546-22.618}{2*0.092} )\\[tex]Cpk=min(1.61 ,5.04 )\\\\Cpk=1.61[/tex]\\\\[/tex]
The Cpk for the process is 1.61, so is a good indicator even with the control of two standard dev.