Respuesta :
Answer:
D. 900 U
Explanation:
When variance will be calculated and shown on performance report it will be, for entire cost incurred.
For all costs directly related to production that is variable cost, standard will be adjusted based on actual quantity produced, whereas standard fixed cost will not be adjusted based on quantity of units produced as is fixed in nature.
1. Standard Direct labor for actual production = [tex]\frac{30,000}{6,000} \times 5,800 = 29,000[/tex]
Actual expense of direct labor = $29,500
Variance = Standard - Actual = $29,000 - $29,500 = $500 U
2. Standard Direct Materials = [tex]\frac{6,000}{6,000} \times 5,800 = 5,800[/tex]
Actual direct material cost = $6,100
Variance = Standard - Actual = $5,800 - $6,100 = $300 U
3. Standard Variable Factory Overhead = [tex]\frac{12,000}{6,000} \times 5,800 = 11,600[/tex]
Actual variable factory overhead = $11,500
Variance = Standard - Actual = $11,600 - $11,500 = $100 F
4. Fixed Cost Variance = Standard - Actual = $24,000 - $24,200 =
$200 U
Total Variance in Performance Report
Every F has positive value and every U has negative Value
= - 500 - 300 + 100 - 200 = - 900
That is 900 U
Answer:
The correct option is B) 260 F
Explanation:
We can take out controllable margin by subtracting cost F from Sales F,
SALES F - COST F
Taking out SALES F -
Actual sales - Budget sales
where actual sales given - $93,960
budget sales - 5800 units X $16
= $92,800
SALES F = $93,960 - $92,800
= $1160 F
Taking out COST F -
Actual cost - Budget cost
Here cost includes -
Direct material = ACTUAL - BUDGETED
Where actual is given - $6100
and budgeted can be taken out as - $6000 / 6000 x actual units
= $1 x 5800
= $5800
NOTE* here we have divided the given budgeted $6000 by given budgeted units of production which is 6000 units.
Direct material cost = $6100 - $5800
= $300 U
Direct labor = ACTUAL - BUDGETED
Where actual is given - $29,500
and budgeted can be taken out as - $30,000/ 6000 x actual units
= $5 x 5800
= $29,000
Direct material cost = $29,500 - $29,000
= 500 U
Variable factory overhead = ACTUAL - BUDGETED
Where actual is given - $11,500
and budgeted can be taken out as - $12,000/ 6000 x actual units
= $2 x 5800
= $11,600
Variable factory overhead cost = $11,500 - $11,600
= 100 F
Controllable fixed cost = ACTUAL - BUDGETED
Where actual is given - $24,200
and budgeted is given as $24,000
Controllable fixed cost = $24,200 - $24,000
= 200 U
now adding together all of the four cost =
300 U + 500 U + 100 F + 200 U
= 900 U
CONTRIBUTION MARGIN = SALES - COST
= 1160 F - 900 U
= 260 F